Skip to content
Rapid Response

      Desks

      This library

      Layoff Notice

      The Three Exceptions and How Narrowly They Are Read

      Three conditions permit less than sixty days, and none of them permits none. Each has an internal structure the regulation spells out, the employer bears the burden on all three, and one of them applies to closings but never to layoffs.

      Layoff Notice6 min readFederal lawThe three exceptions

      The rear door of an old bus with painted lettering above it and green branches visible through the windows
      Each exception describes a narrow situation, and each requires the employer to prove the situation existed. — Joel Peel joel_m_peel, CC0, source.

      The rule in short

      The statute allows a shortened notice period in three situations. The faltering company exception applies only to plant closings and requires four conditions to be met together. The unforeseeable business circumstances exception turns on a sudden, dramatic and unexpected condition outside the employer's control, tested against commercially reasonable judgment. The natural disaster exception requires the action to be a direct result of the disaster. The employer bears the burden throughout.

      The statute sets out three conditions under which the notification period may be reduced to less than sixty days. None of them removes the obligation. Where one applies, the employer must give as much notice as is practicable and must, at the time notice is actually given, provide a brief statement of the reason for reducing the period in addition to the ordinary contents. The regulation states plainly that the employer bears the burden of proof that the conditions for an exception have been met.

      Faltering company, and its four conditions

      The first exception applies where, at the time notice would have been required, the employer was actively seeking capital or business which, if obtained, would have enabled it to avoid or postpone the shutdown, and the employer reasonably and in good faith believed that giving notice would have precluded it from obtaining that capital or business. The regulation confines the exception to plant closings, excludes mass layoffs, and directs that it be narrowly construed.

      It then breaks the exception into four conditions, all of which must hold. The employer must have been actively seeking capital or business, through financing or refinancing by loans, the issuance of stocks or bonds, internally generated financing, or additional money, credit or business by any other commercially reasonable method, and must be able to identify specific actions taken. There must have been a realistic opportunity to obtain what was sought. What was sought must have been sufficient, if obtained, to avoid or postpone the shutdown, and the employer must be able to demonstrate objectively that the amount would have kept the facility, unit or site open for a reasonable period. And the employer must have reasonably and in good faith believed that giving notice would have defeated the effort.

      The fourth condition is the one that most often fails, because it asks the employer to demonstrate objectively what a third party would have done. The regulation offers a route: the condition may be satisfied where the employer can show that the financing or business source would not choose to deal with a troubled company or with one whose workforce would be looking for other jobs. It also adds a limit that catches larger organizations. The employer's actions are viewed in a company-wide context, so a company with access to capital markets or with cash reserves cannot rely on the exception by looking only at the finances of the site being closed.

      Unforeseeable business circumstances

      The second exception applies to plant closings and mass layoffs alike, where the action is caused by business circumstances that were not reasonably foreseeable at the time notice would have been required. The regulation supplies an indicator rather than a definition: an important sign of a circumstance that is not reasonably foreseeable is that it is caused by some sudden, dramatic and unexpected action or condition outside the employer's control.

      Four examples follow, each qualified by the word might or may. A principal client's sudden and unexpected termination of a major contract. A strike at a major supplier. An unanticipated and dramatic major economic downturn. And a government ordered closing of an employment site occurring without prior notice. None of these qualifies automatically; each illustrates the standard.

      The test itself is framed around judgment. The employer must exercise such commercially reasonable business judgment as a similarly situated employer would in predicting the demands of its particular market, and is not required to accurately predict general economic conditions that may also affect demand. The comparison is with a peer, and the subject is the employer's own market rather than the economy.

      ExceptionApplies toCore testDistinctive limit
      Faltering companyPlant closings onlyFour conditions, all requiredAssessed company-wide, not site by site
      Unforeseeable business circumstancesClosings and mass layoffsSudden, dramatic and unexpected condition outside controlPeer standard of commercially reasonable judgment
      Natural disasterClosings and mass layoffsFlood, earthquake, drought, storm, tidal wave or similarMust be a direct result of the disaster
      All threeReduced notice, never no noticeAs much notice as is practicableA brief statement of the reason is required
      All threeContested afterwardsBurden of proof on the employerContemporaneous evidence is what carries it

      Natural disaster, and the gap beneath it

      The third exception applies where a closing or mass layoff is due to any form of natural disaster. The statute names a flood, an earthquake and a drought; the regulation adds storms, tidal waves or tsunamis and similar effects of nature. To qualify, the employer must be able to demonstrate that the closing or layoff is a direct result of the disaster.

      The directness requirement creates a gap that the regulation itself identifies and fills. Where a closing or mass layoff occurs as an indirect result of a natural disaster, this exception does not apply, but the unforeseeable business circumstances exception may. A plant destroyed by a flood falls in the first category; a plant closed because a flood elsewhere destroyed its only supplier falls in the second, and has to satisfy the sudden and dramatic test rather than simply pointing at the weather.

      Even here, notice is not dispensed with. The regulation states that while a disaster may preclude full or any advance notice, such notice as is practicable, containing as much of the required information as is available in the circumstances, must still be given, whether in advance or after the fact of an employment loss caused by the disaster.

      Exceptions are not the same as exemptions

      Separate provisions remove some actions from the statute altogether: the closing of a temporary facility, the completion of a project where employees were hired on that understanding, and a strike or a lockout not intended to evade the statute. Those are exemptions, and no notice is owed at all. The three exceptions here only shorten the period. Confusing the two produces the worst outcome available, which is no notice given where a shortened one was required.

      What actually carries the burden

      All three exceptions are proved with material created before the decision, not after it. For the faltering company exception, that means the record of who was approached for capital or business, when, on what terms and with what response, together with the analysis showing the amount sought would have kept the site open. For unforeseeable circumstances it means the contemporaneous record of what the employer knew about its market and when the triggering event became known. For natural disaster it means the causal chain between the event and the shutdown.

      Two further provisions soften the consequences without changing the tests. Where an exception applies, the shortened notice still has to be given and still has to say why, which is treated in giving as much notice as possible when an exception applies. And where a violation is established, a court may in its discretion reduce the liability or penalty if the employer proves the act or omission was in good faith and that it had reasonable grounds for believing it was not a violation, a discretion examined in damages an employer owes for a short notice. Neither of those helps an employer that decided the sixty days were impossible without recording why, and the ordinary rule remains the one described in the sixty days and when the clock starts.

      Points to carry away

      • The faltering company exception applies to plant closings but not to mass layoffs and is to be narrowly construed.
      • It requires active pursuit of capital or business, a realistic opportunity, sufficiency, and a good faith belief that notice would have defeated it.
      • The employer's financial position is assessed company-wide, not at the site being closed.
      • Unforeseeable business circumstances turn on a sudden, dramatic and unexpected action or condition outside the employer's control.
      • The test is the commercially reasonable business judgment of a similarly situated employer.
      • The natural disaster exception requires the action to be a direct result, and an indirect result falls back on the second exception.

      Questions readers ask

      Why does the faltering company exception exclude mass layoffs?

      The statute confines it to a shutdown of a single site of employment, and the regulation states plainly that the exception applies to plant closings but not to mass layoffs and should be narrowly construed. The rationale is bound up with the condition on which the exception rests: that giving notice would have precluded the employer from obtaining capital or business needed to keep the facility open. An employer conducting a reduction in force while continuing to operate is not in that position, so the exception has nothing to attach to.

      Does a government-ordered closure count as an unforeseen circumstance?

      It can. The regulation gives a government ordered closing of an employment site that occurs without prior notice as an example of a business circumstance that may not be reasonably foreseeable, alongside a principal client's sudden and unexpected termination of a major contract, a strike at a major supplier, and an unanticipated and dramatic major economic downturn. The word may is doing work in that sentence: each example is an illustration of the sudden, dramatic and unexpected standard rather than a category that qualifies automatically.

      What is the employer expected to have foreseen?

      The regulation frames the test around business judgment. The employer must exercise such commercially reasonable business judgment as a similarly situated employer would in predicting the demands of its particular market. It then adds a limit in the employer's favor: the employer is not required to accurately predict general economic conditions that may also affect demand for its products or services. The standard is therefore about market-specific foresight rather than macroeconomic forecasting.

      Sources

      1. 29 U.S.C. 2102 — Notice required before plant closings and mass layoffsContains the three statutory conditions permitting a reduced notification period and the duty to give as much notice as practicable.
      2. 20 CFR 639.9 — When may notice be given less than sixty days in advanceSets out the four conditions of the faltering company exception and the tests for the other two, and places the burden on the employer.
      3. 29 U.S.C. 2103 — ExemptionsThe separate exemptions for temporary facilities, completed projects, strikes and lockouts, which operate differently from the three exceptions.
      4. 20 CFR 639.5 — When must notice be givenExplains the temporary employment exemption and the treatment of strikes and lockouts, including notice to non-strikers.
      5. 29 U.S.C. 2104 — Administration and enforcement of requirementsPermits a court to reduce liability where the employer proves good faith and reasonable grounds for believing there was no violation.
      6. California Labor Code section 1402.5A state analogue conditioning relief from notice on a determination by the state department rather than on the employer's own view.

      Rapid Response Law is a publication, not a law firm. This article states general rules and cites its sources; it is not advice about any particular case, and the law differs by state and changes over time.

      More in Layoff Notice

      Layoff Notice

      Giving as Much Notice as Possible When an Exception Applies

      Where a statutory exception applies, the employer must give as much notice as is practicable to the union, non-represented employees, the state dislocated worker unit and the unit of local government, and the regulation acknowledges that in some circumstances this may be notice after the fact. At the time notice is actually given, the employer must also provide a brief statement of the reason for reducing the notice period, in addition to the ordinary content elements.

      6 min readFederal law

      Layoff Notice

      What Counts as a Single Site of Employment

      A single site of employment can be one location or a group of contiguous locations, and a campus or industrial park may be one site. Separate buildings not in immediate proximity may still be one site where they are reasonably close, used for the same purpose and share staff and equipment. Contiguous buildings with separate management, different products and separate workforces are separate sites. Mobile and outstationed workers belong to the home base from which their work is assigned.

      7 min readFederal law

      Layoff Notice

      State Statutes That Demand More

      State notice statutes depart from the federal model in four directions. California sets coverage at a seventy-five person establishment and counts a mass layoff at fifty separations without any percentage test. New York halves the employer threshold, sets closings at twenty-five and requires ninety days. Maine requires ninety days to a state official before a closing or relocation and imposes severance pay of one week per year of service.

      7 min readState law